China's first domestic photovoltaic power station start making money
Time:2013-05-21

In October last year after the State Grid Corporation announced the introduction of "free access, full acquisition" policy for distributed photovoltaic power, the country's first family photovoltaic plant in Qingdao, Shandong and power generation, currently running in good condition. The industry believes that tariff should soon improve, new energy subsidies, management and maintenance of national standards and other supporting policies to promote the orderly domestic photovoltaic applications. 


18 years to recover the cost 


December 21, 2012, Qingdao City, North Ridge Ditch folder Palit Road, Building 9, residents XuPengfei district erected on the roof of Qingdao grid photovoltaic power smoothly incorporated, becoming the nation's first network of families achieve and photovoltaic power. The photovoltaic power in normal operation so far, the average power over 5 kwh per day, of which the Internet about 3 kWh. 


Until April 22 this year, XuPengfei family small "power plant" cumulative generating 846.73 kwh, electricity revenues exceeded expenditures over the same period the family used electricity grid company. This means removing the cost of PV modules, XuPengfei photovoltaic "power plant" has begun for his money. To May 9, XuPengfei home photovoltaic "power station" total power has exceeded 1,000 kWh. 


Reporters on the scene saw nine polycrystalline silicon solar panels divided into two groups standing sunny, accounting to the roof area of about 1/10, around the various solar water heater is very eye-catching. 


According to XuPengfei introduction, the rooftop PV projects installed capacity of 2 kilowatts, the design life of 25 years, the "self-occupied, I power-line" mode of operation. Due to a discount when buying components, combined with their own installation, engineering, invested a total of about 2.1 million, the current tariff in accordance with the desulfurized coal price 0.4469 yuan / kwh, is estimated to take 18 years to recover the investment. 


Reporters learned that, after the country's first domestic photovoltaic power plants and network successfully, the grid company levels consulting, visitors will flock. According to the State Grid Corporation of statistics, by the end of February this year, the country has 19 provinces, at least more than 170 households applied for individual photovoltaic power and network services, distributed solar heat is increasing. 


Still faces many challenges 


Wang, general manager of the State Grid lines in Qingdao, Shandong power company says with a clean and efficient distributed photovoltaic advantages of in situ use in recent years has become an important direction for the development of national energy and electricity. But our distributed PV has just started, accelerate the promotion still faces many challenges: 


First, the lack of legal regulations. Qingdao, Shandong power company National Grid chief engineer Liu Yan said that the current natural investment distributed photovoltaic power generation projects, yet can not be industrial and commercial registration, the project can not be approved and power business license for not issuing VAT invoices can not be settled grid electricity tariffs This may hinder the development process of distributed photovoltaic power generation families. 


Second, the high cost, can not enjoy state subsidies. Personal photovoltaic power long payback period, and photovoltaic power does not work at night, relatively low efficiency. From the experience of foreign development of photovoltaic power point of view, it all depends on the rapid development of high government subsidies, while China has not yet issued for the construction of a natural use of photovoltaic power generation system of subsidies or price subsidies. 


Third, the architectural design lag, limited installation space. China's population and more and more high-rise residential building in the main, limited roof space.And although residential building facades can be installed, but not at right angles with the sun, it is difficult to achieve maximum power.


Fourth rooftop PV involves many tenants and property companies, stakeholders, installation coordination difficult. To prevent disputes, Qingdao Power Company currently requires household photovoltaic power grid Applicants must provide signed neighbors, property companies and the neighborhood. But many residents of large cities, mostly F-rise buildings, a unit may have a hundred residents, coordination very difficult. 


Formulate supporting policies should be intensified 


For our family photovoltaic new situations and problems arise, "ice-breaking" after some power experts, photovoltaic companies and user recommendations: 


First, the relevant policy should be introduced as soon as possible, the individual photovoltaic power application procedures, approval requirements, rights protection, and other areas of responsibility to make it clear that incorporate standardized management. Suggested business, financial, tax and other departments as soon as possible to build distributed photovoltaic natural industrial and commercial registration, subsidy standards, making clear that invoice and green channels. 


Secondly, as soon as possible to improve the distributed feed-in tariff policy. Deputy director of the State Grid Corporation of Development and Planning Department Zhangzheng Ling suggested that the individual distributed photovoltaic power into the national scope of subsidies, subsidies based on actual photovoltaic power generation. At the same time, to encourage the introduction of distributed PV "spontaneous use" policy to address the current portion of the user to enjoy state subsidies, "enthusiastic Internet, unwilling to use" issue. Except for I give national electricity grid electricity subsidies, electricity for self-occupied, can also be considered for a fixed price subsidies. 


Third, the establishment of PV electricity price linkage mechanism between the scale and development, according to the introduction of the total subsidy ceiling price subsidies. 


State Grid Energy Research Institute, said Zhang Yunzhou, photovoltaic power development is very sensitive to price policy, suggested that the state explicitly limit the total annual PV subsidy to build photovoltaic electricity linkage mechanism between the scale and development, in order to avoid subsidies appear deficit; strengthen Renewable energy subsidy funds to finance management to ensure full funding of subsidies, the timely release. 


Finally, as soon as the introduction of standards and testing and certification of photovoltaic products, strengthening of distributed PV facilities maintenance and management. Proposed to strengthen product standards and testing and certification of photovoltaic systems and build a product list of qualified suppliers, and dynamic management, in order to ensure that users and grid security. In addition, due to the small-scale distributed PV projects, distribution of scattered, often without special management put into operation, there is a big security risk, you should consider the establishment of a dedicated power plant maintenance teams in distributed photovoltaic relatively concentrated areas.


Back
主站蜘蛛池模板: 亚欧av口爆吞精久久久一区二还 | 水蜜桃av无码| 丰满少妇高潮惨叫久久久一| 天堂网www在线资源网| 久久人人爽人人爽人人片av不| 国产绳艺sm调教室论坛| 999久久久免费精品播放| 成年黄页网站大全免费无码| 久久香蕉综合色一综合色88| 尤物av无码国产在线看| 亚洲色大成网站www国产 | 亚洲爆乳精品无码一区二区| 国产目拍亚洲精品二区| 无遮挡啪啪摇乳动态图gif| 性生大片免费观看668| 久久婷婷五月综合尤物色国产| 国产男女猛烈无遮挡免费视频网站| 欧美激情一区二区三区aa片| 精品麻豆丝袜高跟鞋av| 亚洲熟妇av综合网| 无码一区二区三区爆白浆| 满春阁精品a∨在线观看| 国产第19页精品| 性欧美牲交xxxxx视频欧美| 中文字幕av久久一区二区| 一本大道无码av天堂| 亚洲午夜精品a级一区二区| 久久亚洲精品国产亚洲老地址| 日韩精品无码免费专区网站| 大学生高潮无套内谢视频| 日韩一区二区三区久久99 | 欧美精品黑人粗大破除| 中文亚洲成a人片在线观看| 亚洲欧洲无码专区av| 亚洲制服一区二区三区| 国产精品亚韩精品无码a在线| 18禁勿入午夜网站入口| 优优人体大尺大尺无毒不卡| 人人澡人人妻人人爽人人蜜桃麻豆| 日韩av一区免费观看| 亚洲欧美日韩二三区在线|